Nmims April customized assignments - Create a RACI chart for _Our Software Project_ as per the WBS shown below, for the project management roles of project sponsor, project manager
Nmims April customized assignments - Create a RACI chart for _Our Software Project_ as per the WBS shown below, for the project management roles of project sponsor, project manager
Nmims April customized assignments - Create a RACI chart for _Our Software Project_ as per the WBS shown below, for the project management roles of project sponsor, project manager
Nmims April customized assignments - Create a RACI chart for _Our Software Project_ as per the WBS shown below, for the project management roles of project sponsor, project manager
For answersheets contact
info.answersheets@gmail.com
+91 95030-94040
Project Management
1. Create a RACI chart for “Our Software Project”
as per the WBS shown below, for the project management roles of project
sponsor, project manager, customer, and business analyst and software
developer.
2. You are a project manager with Striker Projects Pvt.
Ltd. As the project manager, you need to evaluate two projects “Salient” and
“Stylish”, and make a recommendation to management for the selection of a
suitable project. Both the projects “Salient” and “Stylish” entail an initial
investment of ₹5, 00,000.
Projected cash inflows for the Project “Salient” are ₹1,50,000 in year 1; ₹1,60,000 in year 2; ₹1,70,000 in year 3, and ₹1,65,000 in year 4. Projected cash inflows for the
Project “Stylish” are ₹1,40,000 in year
1; ₹1,40,000 in year
2; ₹1,40,000 in year
3, ₹1,25,000 in year
4; and ₹1,22,000 in year
5. The required rate of return is 10%. The present value of ₹1 at 10% is ₹0.909 for year 1, ₹0.826 for year 2, ₹0.751 for year 3, ₹0.683 for year 4, and ₹0.621 for year 5. Calculate Net Present Value
(NPV), Internal Rate of Return (IRR) and Profitability Index (PI) for both the
projects “Salient” and “Stylish”. Compare and contrast NPV, IRR and PI values
of projects “Salient” and “Stylish”, and recommend a suitable project for
investment to the management. (10
Marks)
3. A project “Suprio” comprises of 9 activities of
varying durations and dependence on previous activities. These activities,
along with their precedent relationships, and their 3-point estimates of
optimistic, most likely and pessimistic duration are given in the table below.
|
Project
Activity
|
Precedent
Activity
|
Activity
Duration (Days)
|
||||
|
Optimistic
|
Most Likely
|
Pessimistic
|
||||
|
A
|
--
|
4
|
6
|
8
|
||
|
B
|
--
|
5
|
7
|
9
|
||
|
C
|
A
|
4
|
7
|
10
|
||
|
D
|
B
|
6
|
8
|
10
|
||
|
E
|
C,D
|
3
|
6
|
9
|
||
|
F
|
C,D
|
4
|
6
|
8
|
||
|
G
|
E
|
3
|
6
|
9
|
||
|
H
|
F
|
3
|
5
|
7
|
||
|
I
|
G,H
|
4
|
6
|
8
|
||
|
|
|
|
|
|
|
|
a. Draw the network diagram of project “Suprio” and
also determine the critical path for the completion of project “Suprio”. (5 Marks)
b. Calculate the expected time of completion of
project “Suprio” based upon the 3-point estimates. What is the probability that
project “Suprio” would be completed within 37 days? (5 Marks)
![]() |